Turlock intersection upgrade in progress

March 13, 2015 | By | No Comments

The project is an intersection signalization.  GRI is a sub-contractor to St Francis Electric.  GRI is performing ADA upgrades and reconfiguration of Pedestrian Ramps, Reconfiguration of a median island to Turn E Zeering Rd into a one way street.  Additionally the relocation of a fire Hydrant and repair of ponding areas in the left turn pocket on west bound Christoffersen Pkwy.  GRI portion of work will be complete this week with total project completion in about 2 weeks.